    Construction Progress

    August 21, 2010
    Many things being done at once.  Plumber has the children’s untis done. (see Pic)  His big job is now the outside pipes and manholes.
    Electrician will begin next week.  The waste management group is on schedule. Major roof complete, only two front sections left.
    Started placing drain gutters yesterday.  (see Pic). They blend nicely.
    Finishing for windows, floors going on daily.
    We will proceed with Solar Hot Water.  The Solar Power is planned but will not install unless and until we have the money to do.   We need $22,000 for solar power. I have re-viewed and  re-worked all the specs with Ghan Power.  Niley do we have any solar groups that could contribute money?
    • Many things being done at once.  Plumber has the children’s untis done. (see Pic)  His big job is now the outside pipes and manholes.
    • Electrician will begin next week.  The waste management group is on schedule. Major roof complete, only two front sections left.
    • Started placing drain gutters yesterday.  (see Pic). They blend nicely.
    • Finishing for windows, floors going on daily.
    • We will proceed with Solar Hot Water.  The Solar Power is planned but will not install unless and until we have the money to do.